If you have ever been asked to provide "ELV drawings" or "ELV design" for a building, the first question is usually what is meant by ELV. The term is used loosely, and it means different things in different standards, markets and trades. Understanding the definition is the first step in scoping the work correctly.

This article explains what extra low voltage means, what ELV stands for, how the term is used in building engineering, which systems are typically included, how ELV differs from mains power distribution, and what design deliverables a project needs. It is general educational information. Project requirements must be checked against the applicable standards and local regulations.

What Does Extra Low Voltage Mean?

Extra low voltage (ELV) is a voltage band below the levels used for ordinary mains supply. The purpose of the band is to limit the risk of electric shock, and to allow circuits to be installed and maintained with reduced protection measures, provided the arrangements meet the requirements for the circuit type.

The exact limit is not universal. International standards define ELV in terms of the maximum voltage that can be maintained under specified conditions, which depends on environment and touch-voltage assumptions. Commonly cited figures for AC and DC systems, such as 50 V AC and 120 V DC ripple-free, appear in several references, but the limit that applies to a particular installation depends on the standard, the edition and the conditions. Always confirm the figure against the standard your project uses.

What ELV Stands For

ELV stands for extra low voltage. In building engineering the abbreviation is used for systems that operate at low energy and that carry signals, data or control information rather than bulk power. Some documents also use ELV to describe extra-low-voltage lighting or appliances, so check the context before relying on the term.

How the Term Is Used in Building Engineering

In a building project, ELV is commonly used as a collective term for the systems that sit alongside mechanical and electrical services. Its scope varies by client and region. Some projects use ELV to mean all low-energy systems; others use it more narrowly for security, communication and control. The first step in any project is to list the systems included in the ELV scope and to agree the responsibilities for each.

Typical ELV Systems in Commercial Buildings

SystemTypical purposeCommon design deliverables
CCTVVideo surveillance and recordingCamera layouts, cable routes, recorder schedules
Access controlDoor control and credentialsDoor schedules, controller layouts, cable schedules
Structured cablingData, voice and wireless backhaulOutlet layouts, riser diagrams, cable and patch schedules
Fire alarm signallingDetection, alarm and signallingDevice layouts, zone plans, cause and effect
PA/VAAnnouncements and emergency voiceSpeaker layouts, zoning, amplifier schedules
Building managementMonitoring and controlPoint lists, sensor layouts, control schematics

ELV Systems vs Electrical Power Distribution

The difference between ELV systems and power distribution is one of purpose and risk. Power distribution carries energy to equipment and lighting, at voltages that can cause serious injury. ELV systems carry information or low-energy control signals. Some ELV equipment is supplied from a mains-powered power supply, and the boundary between the two must be designed carefully. The supply, its protection and its separation from ELV circuits are covered by the electrical design rather than by the ELV scope.

Typical ELV Design Deliverables

A typical ELV design package includes:

  • System layouts on architectural base drawings
  • Riser diagrams and schematic or block diagrams
  • Equipment schedules and rack elevations
  • Cable schedules and containment routes
  • Specifications and device lists for procurement and tender
  • Coordination drawings showing containment and clearances

Cable Routing, Segregation, Coordination and Documentation

ELV cables must be routed so that they can be installed, maintained and identified. Segregation from power cables is a common requirement, and the separation distance and method depend on the standard and the cable type. Containment should be coordinated with mechanical and electrical services early, because late changes to ceiling or riser layouts are expensive. Every cable route and termination should be documented so that the installed system can be verified and maintained.

The Importance of Applicable Electrical Safety Requirements

ELV does not mean exempt from electrical safety. The protective arrangements for an ELV circuit depend on how the circuit is supplied and how it is separated from other circuits. The distinctions between SELV, PELV and FELV are explained in our articles on SELV and PELV. The requirements are set by the electrical installation standard in force and by local regulations, and they should be confirmed by a qualified electrical engineer.

When a Project Needs an ELV Design Consultant

An ELV design consultant is useful when:

  • A building includes several ELV systems that must be integrated
  • The design must meet fire, security or cabling standards
  • Drawings must be coordinated with architectural and MEP information
  • The client needs a tender-ready specification and layout package
  • An existing system is being extended or replaced

ASDV Consultant provides ELV and ICT design consultancy, including the layouts and documentation described above. Our services overview lists the systems we design, and you can contact us to discuss your project.

Frequently Asked Questions

Extra low voltage (ELV) refers to a voltage level low enough that contact with a live part is not normally expected to cause serious harm under defined conditions. The exact limit is set by the electrical standard in force, and depends on whether the supply is AC or DC, the environment and the earthing arrangement. It is not a single universal number.
ELV stands for extra low voltage. In building engineering the term is used for low-energy electrical systems such as data, control, communication and signalling circuits. The same abbreviation is also used in some documents for extra-low-voltage lighting and other applications, so the context matters.
No. Low voltage (LV) in power engineering usually refers to mains-level distribution, commonly up to around 1 kV, while ELV is a lower band intended for limited-energy and safety-related circuits. Terms and bands are defined differently in different standards, so always check the definition the project uses.
Typical ELV systems include CCTV, access control, intruder detection, structured cabling for data and telephony, fire alarm signalling, public address and voice alarm, intercom, building management system sensors and certain lighting control circuits. The systems included depend on the building and its specification.
Usually not. ELV design normally covers the signalling, data and control systems. Mains power distribution, lighting power circuits and equipment supplies are designed separately under the electrical installation. ELV design must still coordinate with power supplies and containment.
A consultant is useful when a building has several ELV systems to integrate, when the design must meet fire, security or cabling standards, or when the drawings need to be coordinated with architectural and MEP information. The consultant defines the design and documentation, while electrical safety compliance is confirmed by the appropriate licensed professionals.