ELV Deliverables by RIBA/RIAI Work Stage in Ireland

ELV design is not a single deliverable — it is a programme of deliverables that evolves through the RIAI work stages. Understanding what ELV deliverables are appropriate at each stage — and critically, why producing Stage 4 deliverables at Stage 3 or Stage 2 deliverables at Stage 4 is problematic — is essential for Irish project managers, architects and M&E consultants who are managing ELV consultants as part of a design team. This guide maps the ELV deliverable requirements to each RIAI work stage, with specific reference to Irish NDP projects, BC(A)R documentation requirements and ISO 19650 LOD progression.

Why ELV Deliverables Must Be Staged — Not Issued All at Once

ELV design deliverables are staged because each stage of design depends on information that only becomes available as the project develops. A Stage 2 fire alarm category cannot be determined without a fire risk assessment — which requires the building layout to be sufficiently defined. A Stage 3 detector layout cannot be clash-checked in BIM without a coordinated structural and MEP model — which only exists at Stage 3. A Stage 4 cause-and-effect matrix cannot be signed off without the MEP engineer's AHU layout and the architect's door release strategy — both of which are Stage 3 outputs. Attempting to produce all ELV deliverables at once — regardless of what information is available — produces design that will need to be revised as the project develops, creating abortive work and programme overrun.

LOD 300
The ISO 19650 Level of Development required for ELV systems at RIAI Stage 4 (Technical Design / Tender) on Irish NDP projects — dimensioned, fully specified, spatially coordinated and clash-detected. LOD 300 is the standard that HSE Capital Programme and OGP public works projects specify in their Employer Information Requirements for ELV discipline models at tender stage.

RIAI Work Stages — A Quick Reference

The RIAI work stages used on Irish building projects are: Stage 0 (Strategic Definition), Stage 1 (Preparation and Brief), Stage 2 (Concept Design), Stage 3 (Developed Design), Stage 4 (Technical Design), Stage 5 (Construction), Stage 6 (Handover and Close Out). This broadly aligns with the RIBA Plan of Work 2020 stages used on many UK-influenced Irish projects. The key design stages for ELV are Stages 2–4; Stage 5 is construction support; Stage 6 is handover documentation.

ELV Deliverables by Stage

Stage 1 — Preparation and Brief
ELV Input to the Project Brief
Confirm ELV consultant appointment and scope. Input to the strategic brief: ELV system requirements based on occupancy type; fire alarm category range (to be confirmed at Stage 2); structured cabling and ICT connectivity requirements; security system risk assessment input; BIM requirement and LOD progression agreement. No design drawings produced at Stage 1.
Stage 2 — Concept Design · LOD 100–200
Fire Alarm Category + System Concepts + Riser Allowances
Key deliverables: (1) Fire alarm category determination statement — the I.S. 3218 category confirmed by fire risk assessment input, documented and agreed with the fire safety consultant and building authority; (2) System concept summary — one-page description of each ELV system proposed; (3) Riser shaft and containment allowances confirmed with structural and MEP teams; (4) BIM discipline model at LOD 100–200 — spatial placeholder showing riser locations and containment zones; (5) Stage 2 ELV design report. The category determination is the most critical Stage 2 deliverable.
Stage 3 — Developed Design · LOD 200–300
Layouts + Coordination Drawings + Draft C&E Matrix
Key deliverables: (1) Detector and device layout drawings on current architectural plans — sufficiently developed for coordination; (2) Zone plans and preliminary riser diagrams; (3) Draft cause-and-effect matrix — major interface logic confirmed with MEP and architect for AHU shutdown, door release, lift return and suppression interfaces; (4) BIM discipline model at LOD 300 — spatially coordinated with structural, architectural and MEP models, clash-detected; (5) Clash detection report; (6) Builder's work drawings identifying structural openings required for ELV services; (7) Stage 3 coordination report documenting interface decisions with other disciplines.
Stage 4 — Technical Design · LOD 300
Full Tender Package — BC(A)R Ready
Key deliverables: Complete tender package including — (1) Final layout drawings incorporating all Stage 3 coordination changes; (2) Complete zone plans and riser diagrams; (3) Signed cause-and-effect matrix; (4) Panel and equipment specifications with IS EN 54 certification references; (5) Performance specifications for installation and commissioning; (6) Bills of quantities (per procurement route); (7) Design basis statement citing I.S. 3218:2019 and all applicable standards; (8) BIM model updated to final LOD 300 — issued through CDE. This is the primary BC(A)R submission package.
Stage 5 — Construction · LOD 300–400
Tender Support + Site Support + As-Built Updates
Key deliverables: (1) Tender query responses — clarifying ELV design intent for tendering contractors; (2) Value engineering reviews — assessing contractor-proposed alternatives; (3) BIM model updated to LOD 400 (where BIM is mandated) as design is confirmed through contractor shop drawings; (4) As-built drawing updates incorporating site changes from tender drawings; (5) Witness of commissioning testing for fire alarm, structured cabling and security systems.
Stage 6 — Handover · LOD 500
As-Built Documentation + O&M Manuals + BIM Handover
Key deliverables: (1) Final as-built drawings — incorporating all site variations, approved design changes and commissioning modifications; (2) O&M manuals for all ELV systems — system descriptions, commissioning certificates, test records, maintenance schedules; (3) BIM model updated to LOD 500 (as-built) for facilities management handover; (4) BC(A)R handover documentation — commissioning certificates for fire alarm (I.S. 3218 compliance), structured cabling (ISO/IEC 11801 channel test results), CCTV and access control; (5) Defects liability period support — responding to post-handover commissioning defects.

ISO 19650 LOD Progression by RIAI Stage

For Irish NDP projects mandating ISO 19650 BIM, the LOD progression for ELV discipline models aligns with RIAI stages: LOD 100 (conceptual spatial placeholder) at Stage 1–2; LOD 200 (approximate size, shape, location and orientation — spatial coordination concept) at Stage 2–3; LOD 300 (dimensioned, specified, coordinated) at Stages 3–4; LOD 400 (fabrication-ready, manufacturer-specific content) in Stage 5 construction; LOD 500 (as-built, verified against site installation) at Stage 6 handover. HSE Capital Programme and OGP public works Employer Information Requirements (EIR) specify the LOD expectations explicitly for each discipline at each stage.

ASDV's Deliverable Schedule for Irish NDP Projects

ASDV produces a project-specific ELV deliverable schedule at Stage 1 appointment — mapping each deliverable to its RIAI stage, issue date, CDE location and review period. This schedule is incorporated into the project's BIM Execution Plan (BEP) for ISO 19650-mandated commissions. The deliverable schedule is updated at each stage gate to reflect any programme changes, with the assigned certifier's review requirements specifically accounted for at Stage 4.

See our ELV design consultant Ireland service page for the full scope, and our ELV resource support Ireland page for extended design team augmentation for NDP pipeline management.

FAQs — ELV Deliverables by RIAI Stage Ireland

Fire alarm category determination statement (the most critical Stage 2 deliverable); system concept summary; riser shaft and containment allowances confirmed with structural and MEP teams; BIM discipline model at LOD 100–200; and Stage 2 ELV design report. No detailed detector layouts at Stage 2.

Draft C&E matrix at Stage 3 (major interface logic confirmed with MEP and architect); final signed C&E matrix at Stage 4 (included in the tender package). Starting the C&E matrix at Stage 4 without a Stage 3 draft is a programme risk — AHU shutdown and door release logic require MEP and architectural input best resolved at Stage 3.

Both are broadly equivalent in structure (0/1–6/7 stages). RIAI Stage 2 (Concept Design) = RIBA Stage 2; RIAI Stage 3 (Developed Design) = RIBA Stage 3 (Spatial Coordination); RIAI Stage 4 (Technical Design) = RIBA Stage 4. For Irish projects, RIAI stage numbering is standard; UK developer-led Irish projects may specify RIBA stages in the professional services contract.

Signed fire alarm design package (layouts, C&E matrix, IS EN 54 equipment schedule, design basis statement); commissioning certificates for fire alarm, structured cabling, CCTV and access control; as-built drawings incorporating all site changes; and O&M manuals for all ELV systems. Commissioning certificates and as-built drawings are the most commonly missing items at Irish practical completion.

LOD 100–200 at Stages 1–2; LOD 300 at Stages 3–4 (standard for Irish NDP tender issue); LOD 400 in Stage 5 construction; LOD 500 (as-built) at Stage 6 handover. HSE Capital Programme and OGP EIRs specify LOD requirements explicitly for each discipline at each stage.

Get a Free ELV Deliverable Schedule for Your Irish Project

Tell us your building type and programme — we confirm the ELV deliverable schedule, stage fees and fixed-fee proposal within 24 hours.

Request Free Schedule

Or: +91-8800334308  ·  WhatsApp Us

ASDV Design Team
ELV Design Consultants — ASDV Consultant Ireland