Structured Cabling Design for Qatar: Ashghal and Kahramaa Infrastructure Requirements
Structured Cabling — ASDV Consultant

Two government authorities — Ashghal, the Public Works Authority responsible for roads and infrastructure corridors, and Kahramaa, the Qatar General Electricity and Water Corporation — both impose requirements that reach into a building's telecoms design well before rack layout and patching schedules.

Ashghal's relevance is at the site boundary and external duct crossing level. Any project requiring external telecoms or fibre connectivity between a building and the public network must coordinate against Ashghal's Underground Utility Network (UGN) design guidelines, which set requirements for how crossing ducts connect with utility corridors and concrete protection beneath carriageways. In practice, the actual civil route needs to be verified against as-built utility records via an on-site survey, since records in a fast-developed city don't always match design intent.

Kahramaa's relevance is a structural decision with ripple effects: Kahramaa strongly prefers, and frequently mandates, that main electrical rooms sit on the ground floor, with room layout requiring Kahramaa sign-off before construction. Telecoms/IT room adjacency planning needs to accommodate a room whose exact footprint isn't finalised until Kahramaa approves it.

Design guidance

Engage Ashghal's UGN requirements at masterplan or site-boundary stage. Commission an as-built utility survey before finalising external duct routing. Sequence telecoms/IT room layout finalisation after Kahramaa's electrical room siting approval where the two rooms are adjacent.

AuthorityWhat it governs for cabling projectsDesign stage to engage
AshghalExternal duct crossings, utility corridor allocationMasterplan/site boundary, before detailed design
KahramaaGround-floor electrical room sitingEarly architectural coordination
Building operator/ITInternal structured cabling standardDetailed design, following the above two constraints

Common mistakes

The most common mistake is finalising internal cabling routing before external civil coordination with Ashghal is complete. A second is treating Kahramaa's electrical room requirement as fixed and known early, when its exact position depends on Kahramaa's own approval process.

Future outlook

As Digital Agenda 2030 pushes higher-capacity digital infrastructure, both authorities are digitising their infrastructure records, which should reduce the as-built discrepancy problem over time.

Frequently Asked Questions

Because external telecoms connectivity physically passes through Ashghal-governed utility corridors, and uncoordinated routing can leave the internal design planned around an unachievable connection point.
Not directly — the relevance is indirect, through electrical room siting that affects adjacent telecoms room layout planning.
Commission a licensed surveyor to verify existing utility locations, since as-built records can lag actual conditions in fast-developing areas.
As early as masterplan or site-boundary design for any project needing external duct connectivity.
The telecoms room's cable containment routing may need redesign if the electrical room's final footprint shifts during approval.